Wahich dates can be copied to which other dates .Like forecast dates, basic date, actual dates, schedule dates. Please mention how can be copied and from which date to which other date.
Zinni
Scheduled Dates( earliest and latest)WBS can be copied to Basic Dates . Forecast dates can be copied from basic dates and vice versa,
For this, go ot Project Plannig board(Gantt Chart). Follow menu path: Edit > Select > WBS Elements. Then follow path: Edit > Reconcile Dates > Copy scheduled dates ( copy scheduled dates to Basic Dates). 2) Edit > Reconcile Dates > Transfer forecast dates to Basic and vice versa.