Dates copied

Former Member
0 Kudos

Hi

Wahich dates can be copied to which other dates .Like forecast dates, basic date, actual dates, schedule dates. Please mention how can be copied and from which date to which other date.

Zinni

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Scheduled Dates( earliest and latest)WBS can be copied to Basic Dates . Forecast dates can be copied from basic dates and vice versa,

For this, go ot Project Plannig board(Gantt Chart). Follow menu path: Edit > Select > WBS Elements. Then follow path: Edit > Reconcile Dates > Copy scheduled dates ( copy scheduled dates to Basic Dates). 2) Edit > Reconcile Dates > Transfer forecast dates to Basic and vice versa.

Regards,

Mahendra

Former Member
0 Kudos

Thanks. Can actual dates too be copied to any other dates and if how??

Zinni

Former Member
0 Kudos

You are welcome. Actual dates do not get copied anywhere else. However when actual dates are put into place, they drive the scheduling for remaining time. I mean actual start drives the scheduling.

Hope this helps to you.

Regards,

mahendra