HI there,
I'm new to PP/DS. It seems that we have planned orders being created in APO & R/3.
Is this possible? And if so how can I check the APO side and which one do I deactivate?
Thanks for taking the time to read my post.
Regards
Robert
Hi Robert,
Planned orders can be created either manually
in APO using transaction /sapapo/rrp3 or through
heuristic job based on demand.
If you establish CIF connectivity based on integration
model between APO & R/3 for planned orders, then
the created orders in APO can be taken to R/3.
On the otherway, if you create any manual planned
orders in R/3, the same will get updated into APO
via CIF (core interface)
Hope your query is resolved. Please confirm
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
13 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.