on 12-10-2009 7:35 AM
Hello,
While creating a PR in CJ20N for a project type material, I am getting an error that
'The material is for individual requirement only, check entry.'
This material in configurable material type & all the settings for configuration are maintained properly as in configuration class, charecteristics etc. This error is only for one plant and not for other all plants.
Is the configuration setting for material plant specific? ( ie. CT04, CL02, CU41)
Can anyone please guide me why this error is coming?
Regards,
Krutika
I think you are using "No stock" indicator in Project profile and the material you assigned has individual requirement type(i.e., can be procured only for Special stocks like Project or Sales order). Make necessary changes in material master for that plan in MRP view, i.e., select "individual and collective requirement"
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.