on 12-10-2009 4:07 AM
Hi All,
I have created MMR for externally procured material with QM view with the following data.
QM in procuerment active,control key is 007,and Inspection type is 01 and stock is posted to Inspection stock.
While doing GR,QI lot is not getting created automatically.Any other settings to be maintained in customizing.
Regards,
Deepak.
Dear Deepak
For external procurement you are doing it through routing then active 0130 inspection type
The in mm02 in qm view activate both 01 and 0130 and maintain preferred indicator tick in 0130
Regards
Gajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Deepak
Please go to QI02, in the status tab there you might have maintained status profile for Supply relation ship (QM_P_001)
Kindly remove the same and then do the GR
Regards
Gajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Go to QP01-->enter material plant valid date(prior to inspection lot creation)
Enter Usage :5
status:4
At char level mainatin char.& save.
In Inspection plan you can put number range as 99999999 .
That's all needed to create Inspection lot provided that for 101 mvt type QM is active & QM view is exists in Material Master.
Sujit
Dear Deepak
Please check this settng
OMJJ > movement type > 101 > Deactivate QM inspection / delivery category > check for the movement type 101 QM not active
Please remove the tick
Regards
Gajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
As you have used 007 key
You must have created QInfo.In Qinfo have you maintained "Inspec control"-"No inspection"
In QM view have you activated QM view ( tick near Preffered insp type")
Have you activated inspec type : 0130 also?
Regards
Sujit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Maintain inspection type(s) 0101 for material XXX
Message no. QB062
Diagnosis
You have planned inspection types for the source inspection or using status management that are not yet active for the material XXX.
Procedure
Activate the inspection types in the inspection setup (Quality Management view of the material master).
I am getting the above error message while I try to post GR.
Any possible resolution methods?
Regards,
Deepak
Hi
This error is due to either:
For source inspection in QI01 you have maintained 0101 inspection type.
As 0101 is for Pilot inspection which is excecuted through status mgt of the Qinfo.
So you have to either active this inspection type in QM view or remove status mgt & source Inspection.
But why you are making it too complex.Keep QInfo record simple & only activete 01.
This will work
Regards
Sujit
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.