on 12-10-2009 2:32 AM
Hi Gurus,
I thought when doing DMR and the status of Quality Level is in Skipped, the Lot will automatically got to unrestricted use? Is this correct.
I'm doing a test and the Lot is not going in Unrestricted use directly. What settings am I missing?
Thanks,
Raymond
Dear raymond
Do mulitple GRs when the lot is in skip and then check the stock
Also please let me know what have you maintained in Inspection control in inspection setup
Regards
Gajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Raymond
The Manufacturer and Manufacturer number is maintained in the material master in the Purchasing view. When PO is made these data get copied to PO
Regards
Gajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Raymond
Have you ticked automatic UD in the inspection setup. if not do it and then check
Regards
Gajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Raymond
If the lot is skip and there is no lot summary happening then the stock will move to unrestricted directly.
If both a skip lot and an automatic usage decision occur, the system performs a ship to stock without posting the material into the quality inspection stock. The ship to stock does not take place during inspection lot summary.
Regards
Gajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Have you Defined that " no inspections" occur in the control for quality info record.
Have you Defined in the inspection setup for the material in the quality management view of the material master, that an inspection only occurs at the first goods receipt for each purchase order or production order.
Sujit
Hi,
This is the one which have check in inspection set up.
post to inspection stock
inspection with task list
automatic assignment
skips allowed
Control insLot : for each material document
I tried again by resetting the Quality level but still it doesnt put the stock to unrestricted.
Thanks,
Raymond
Edited by: Raymond on Dec 10, 2009 3:22 PM
Hi
I thought when doing DMR and the status of Quality Level is in Skipped, the Lot will automatically got to unrestricted use? Is this correct.
I'm doing a test and the Lot is not going in Unrestricted use directly. What settings am I missing?
I presume that status of the lot is "SKIP".
Now go to material document of that lot & check what is Stock type."Unrestricted" or "Quality Inspec"
Also check in MMBE.
Also remember that when lot is skipped ,stock posting is to unrestricted but UD you have to take oe schedule.
So can you please explain the way in which you have applied the DMR.Where applied & what are the stages.
Regards
Sujit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.