Dear All,
I have a requirement as follows: Customer create forecast for Garment on the following planning levels
Customer, Product Group, Material and Location forecast
cust01 , PG_G , Garment, DC01, 10
In DP BOM, 1 dozen of garment will use 2.4 yard fabric
In DP, are we able to achieve the following result ? Note, Garment and Fabric belong to different product group, and Garment has forecast in location DC01, dependant requirement for Fabric should be put on location PL01.
Customer, Product Group, Material and Location dependant requirement
cust01 , PG_F , Fabric, PL01, 24
Thanks,
Bin
Hi,
You can use DP BOM functionality where Garmnt will have PPM with fabric matrial with 1:2.4 ratio. PPM usag will be D.
Here dependnt demand for fabric will be forcasted but on same location. You can check IN PPM by maintaining planning location as DC and production location as Fabric location(This is production in another location) I donot think it will work.
Other Approch is maintain special procurement key for fabric material as stock transfer from plant. Transfer the product to APO it will create T-lane fro fabric material from DC to plant.
Hence dependent requirement of fabric will tranferd to other location through stock transfer request.
Regards,
Siddharth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.