Hi,
I want to maintain two different cost centers belonging to different company codes (one with USD and other with INR) in WBS element level in requesting and responsible cost center field. When I do this, I'm getting an error message stating that "currency in requesting company code must be company code currency". Please let me know how to overcome this issue and maintain cost centers with two different currencies.
Aman
Closing the thread
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Aman,
This is standard functionality cost center company code should be same as WBS company code.
Question:
Why you want to assign cost center's from diferent company code to one WBS element?
Thanks
Aby
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The issue is the responsible cost center (where the work is done) operates in a different country, and requesting cost center (where the work is being requested) operates in a different country. Based on my investigation SAP standard functionality doesn't allow to save these two cost centers in one WBS. Please let me know if there are any other way in SAP to overcome this issue.