on 12-09-2009 6:28 AM
Hi,
I would like to ask about the quality level. I changed the criteria of Dynamic Modification Rule from Vendor-Material to only material. This is because I don't care what vendor delivers a material, i would like to apply skip lot to all.
But after I changed the criteria, the quality level do not update. I also deactivate the check characteristic option. May I know the prerequisite of Qulaity Level? The lots also is not skipping.
Thanks,
Raymond
Dear Raymond
Go to QS23, in that input the mic number and enter and click on control indicator . There in the first screen itself you can see required and optional
Regards
Gajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Raymond
You can do this. Make your characteristic as optional in the control indicator
Regards
Gajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Raymond
1) As you deactivated the vendor from the inspection plan a new quality level will get started with initial stage.
2) if you remove the tick for inspection task list then i believe there will be no effect on the quality level and the dynamic rule will not come into picutre
still if you need DMR rule then you should specify this in QM view inspection setup in DMR . This field is only relevant if you inspect a material without using a task list or material specification. If you enter a dynamic modification rule in this field, the system maintains a quality level for the material, plant, and inspection type.
Regards
Gajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Raymond
If you go to QDL2 now you will be able to for the material 2 different levels appearing. 1 for tasklist / vendor combination and one for only task list
check this task list and let me know whether it showing the correct stage.
Regards
Gajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Yes I see that, I just reset the Quality Level and do another round of test.
What logic do the system follows? I deactivate check tasklist in QM view in material master, does the system still checks for my inspection Plan?
I created Inspection Plan for reporting and forms purpose.
Thank you,
Raymond
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.