on 12-08-2009 12:52 PM
Hello,
in a two-tier landscape I need to define transport targets in SLD. Both PI syetems have their own SLD. In each SLD there is just the Integration server of the corresponding PI system. How to get the DEV Integration Server into PROD sld? Manually?
Thanks,
CHRISTOPH
Hi Christoph,
You have define a transport group in SLD with their individual integration servers.
Provide the same name for the transport group on both the DEV and PROD system.
This should serve the purpose.
Cheers....,
Raghu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Raghu,
thanks, but my question is: In order to create groups in the PROD SLD, I need both the PROD and DEV Integration Server in the PROD SLD.
How to create Integration Server DEV in the PROD SLD? Is there any automatisation (ABAP transaction)? Or manual creation?
I have one SLD per PI system. No sync.
Thanks,
Christoph
Hi Christoph,
You need not sync both the integration server business systems. They can be independent.
I hope you are configuring this for the transporting you IR and ID objects.
In this case just configure the transport group and assign it to business system. Then do the transport and check.
If any issues please revert.
Cheers.....,
Raghu
Hello Seshagiri,
that is what I wanted to know. So there seem to be two possibilities:
- Creating the DEV Integration Server in productive SLD manually
- Exporting the DEV Integration Server from DEV SLD and import it into productive SLD.
I tried importing / exporting SLD content some time ago. AFAIK there is no exporting single technical / business systems, you can just export all the content together from a SLD?
Thanks,
Christoph