on 12-08-2009 11:30 AM
Hi
We have configured Charm the process is working fine , i want to deactivate the old procedure of releasing request in SE03 and ensure that requests can be imported or moved only through charm . can anyone help on how to deactivate the old procedure of transport mgmt with out disturbing charm.
Thanks
Nanda
Nanda
goto SE03 in your satelite system
Display/Change Request Attirbutes
open SAP_CTS_PROJECT
put in your develiopment client and mark the field "required"
nesimi