on 12-08-2009 8:42 AM
Hi All,
I am trying to use Mass Change Function to change one field value in my Standard project Definitions as well as Standard WBS Elements but its not doing.Is it that Mass change Function is only aplicable for Operative projects and not for Standard Templates?
Expecting your response on this.
Thanks and Regards,
Harsh Shekhar.
your observations are correct - mass change functions are only for oprative pojects and not for standard templates
you can try LSMW