on 12-08-2009 7:54 AM
Hi,
i would like to know if its possible to block posting in the usage decision screen and do manual posting through MM transaction?
This is a requirement that QM user has no authorization transferring the goods to unrestricted stock. Only Warehouse will be allowed to do stock transfer.
Thank You,
Raymond
Please speak to your BASIS person and allow Quality Person to do UD without postings and allow Warehouse Person to do postings through QA12 Transaction.
Best Regards,
K. Raghavendra Nayak
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
So let me clear things up. I can do Usage decision and accept the lot without having stock posting yet. This will have no impact, correct?
Then, i can do stock posting via qa12 correct?
Yes this is Ok but make sure that in selected set of UD code in QS54-->stock posting proposal is blank of any UD code.
can i use qac2 instead?
Yes this can be very well used.
Regards
Sujit
I beleive you could also do this via status control.
Set up user status that prevents stock posting until the UD is complete. Add statuses to block the UD and/or stock postings. Assign the two groups of users to different auth groups. assign to the correct user statues.
User status
INIT --- Use this to block the stock postings and UD
MKUD - Make UD - Assign that only QM folks can set this status
After UD is made, have it set
STPT - stock posting - block QM folks from this and allow WH folks.
Craig
Hi
It is not possible.How come Quality trnascations possible through WM or IM.it will through an Error that "transaction is possible through Quality only"
What you can do is remove the tick of "Post to inspection " in QM view of inspection type.
This will post material to Unrestricted & then You have only Inspection lot which you can refer for Quality perpose.
But belive me this is really loose control in any organization if Quality does not have authoriry of QI t codes ...
Then what is use of Quality????
Sujit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
This is customer requirement because warehouse and quality have some conflict. Warehouse doesnt want the quality doing goods movement as warehouse is afraid they cannot trace those stock which will be transferred by quality.
Quality also agreed on this one that it should be the store which would move those material.
Thanks,
Raymond