Dear Guru's,
Can you please explain me How to download Project Gang chart in to Excel? Please explain me all the steps to download.
Regards,
Sai
Edited by: Virendra Pal on Dec 8, 2009 10:02 AM
hi,
you mean Gantt chart.
a gantt chart is basically a graphical representation of the activities/wbs element based on the dates/durations...
it can be directly downloaded to ms project if you have open PS..
however, if you are using excel, you can easily derive the gantt chart based on the start and finish dates (planned/basic/actual/forecast dates) of the objects...
you can access CN41N then go to Evaluation > Export > Spreadsheet..
with this you can derive the gantt chart based on the data..
regards.
Edited by: Virendra Pal on Dec 8, 2009 10:03 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
9 | |
9 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.