on 12-07-2009 5:37 PM
Hello APO Gurus,
I'm trying to CID SNP PDS from ECC 6.0 into APO. My recipe has overlapping phases, with an offset defined.
While trying to CIF the SNP PDS, it gives an error "The relationships are inconsistent".
Pl advise.
With Regards,
Mangesh
Hello APO Guru's,
Could anyone pl provide insigths on how to create SNP PDS with overlapping operations/phases?
Else our master data maintenance for recipe would increase to create a separate recipe for SNP PDS with linear relationship.
Thanks in advance.
With Regards,
Mangesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Tibor,
I checked all the notes and none of them applies to our release, as we are on SCM 7.0.
Is there any other setting that needs to be done?
Thanks and Regards,
Mangesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Mangesh,
please check whether following notes are already implemented in your system:
954439
908782
914368
853241
I hope I could help.
Regards,
Tibor
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.