How to CID SNP PDS with overlapping operations/phases?

Former Member
0 Kudos

Hello APO Gurus,

I'm trying to CID SNP PDS from ECC 6.0 into APO. My recipe has overlapping phases, with an offset defined.

While trying to CIF the SNP PDS, it gives an error "The relationships are inconsistent".

Pl advise.

With Regards,

Mangesh

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hello APO Guru's,

Could anyone pl provide insigths on how to create SNP PDS with overlapping operations/phases?

Else our master data maintenance for recipe would increase to create a separate recipe for SNP PDS with linear relationship.

Thanks in advance.

With Regards,

Mangesh

Former Member
0 Kudos

Hi Mangesh

I am facing the same problem. SNP PDS is not getting ciffed over with overlapping operation.

Do you have implemented any development or OSS note to achive the same.

Hrishikesh

sb_fernandes
Participant
0 Kudos

I too had the same issue.By maintaining the reletionship in Recipe it got fixed.

Former Member
0 Kudos

Hello Tibor,

I checked all the notes and none of them applies to our release, as we are on SCM 7.0.

Is there any other setting that needs to be done?

Thanks and Regards,

Mangesh

tibor_nagy
Contributor
0 Kudos

Dear Mangesh,

please check whether following notes are already implemented in your system:

954439

908782

914368

853241

I hope I could help.

Regards,

Tibor