on 12-07-2009 3:21 PM
hi experts
i need to implement a change in va01 i.e when we save order and at time of delivery if we wish to change the plant the variant characteristics should not change is it possible in ECC6.
But generally when plant is chnaged and we hit enter or press save it changes the VC also but we do not want VC to change .
Hello Sunny,
the change of the configuration after the change of the plant is standard. But you can use userexit_move_field_to_vbap in include MV45AFZZ to move the old configuration from *VBAP-CUOBJ to VBAP-CUOBJ. then the old configuration is still present.
Best regards,
Jörg
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.