Plan Component from Maintenance Order

Former Member
0 Kudos

Hi,

When i plan a component from maintenance order I use item category N with key MATE.

But i woul plan component for purchase requisition on project stock( account assign Q) directly from Maintenance Order. Allow I insert item category N in the field ad near insert the value 2 for project stock.

When i release the order the system blank the field and i don't create a Purchase requisition with project stock but i purchase requisition with account assignement F

Because the system put away the field blank?, I must done another customizing, or i must utilize another KEY?

Thank you

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

When you make Item cat as N it means they are non stock .

For non stock & with F order as account assignment system creates PR.

if you want this componenet as Project stock them there are following ways

1.Make PR with item cat as Q & make PR on WBS or PS System.

System will post direct entries.

2.Make normal stock PR then issue against WBS by order

Settle the maintenance order to WBS element

3.Get material as normal stock material issue with 221 mvt against WBS or PS system.

Systme will make enties to WBS.

Ramesh