Remaining order plan value in RPSCO table

Former Member
0 Kudos

Hi

The remaining order plan value is seen in report S_ALR_87013558, but cannot be seen in table RPSCO against value type 25.

Any guesses where the problem could be?

Or any suggestion on how else to get the remaning order plan value directly from tables.

Regards

Srikrishna

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

closed the thread

Former Member
0 Kudos

Hi Srikrishna,

Happy New Year 2010, could you please refer to note 152571 and perform the below?

1) Please run report RKANBU01 for the incorrect projects in question

This will update any incorrect commitments. Further details can

be found in the note above.

2) After running the reports above, please run report RKACOR04

as this will correct any problems between the line item tables

and the total record tables.

3) After running the above reports, please run transaction CJEN

for all the projects as this is very important so that the

database gets updated.

Could you also run transaction CJVC for the given controlling area? If you see any yellow

or red flags then, you must delete them and rebuild table RPSCO via CJEN (please review

note 676123 for this regard).

Thanks a lot and kind regards,

Enrique Sosa