on 12-04-2009 3:54 PM
Hi,
I would like to share our scenario in QM. Currently We have separate Storage Location for Quality Stock (IQA) and Unrestricted Stock (MS).
How will the system behave during Skip lot? Does the stock goes IQA Unrestricted or in MS Stock?
If stock goes to IQA unrestricted, may I know how will I set in the system that Skip Lot will auto UD as accepted and stock goes to MS storage Location as unresticted?
Thank you,
Raymond
Hi
How will the system behave during Skip lot? Does the stock goes IQA Unrestricted or in MS Stock?
When lot is skip you know it moves to unrestricted.Now in your case there are Two Unrestricted storage Locations.
Always remember that stock always moves to "Storage Location on which GR is made" it is depend upon the MIGO.
So If you want to move the material form one storage to other then use MB1B-->311 mvt type.
I hope this is clear
Regards
Sujit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I understand, but we have 2 storage location so we need to do stock transfer. Also we have two types of skip, 1 is auto UD, other is manual UD. how can we segregate in the variant?
So this is a batch job, that would be run daily?
What do you mean also by maximum skip duration?
Thanks,
Raymond
but we have 2 storage location so we need to do stock transfer. Also we have two types of skip, 1 is auto UD, other is manual UD. how can we segregate in the variant?
Dear this varient is for Usage Decision.Both Manual & auto will be covered here.Its can only be differtiated by the Stock posting tab & status(SPRQ/SPCO) which is missing in manual cretaion.otherwise its difficult to seggregate.
So this is a batch job, that would be run daily?
this you can run per hr,per day etc.We have practice of executing this per 30 min.It very much depend on server load.
What do you mean also by maximum skip duration?
Time (after creation of lot) till which system should not take UD of the lot.Means your varient run say after every 1 hr.and time in maximum skip duration say you have mainatined 2 hrs then ,,,,,,system will only take ud of those lots which were created 2 hrs before the varient run every 1 hr.
I hope I have made you clear
Regards
Sujit
Hi Raymond,
As per best of my understanding, when we talk about the skip lots it doesn't mean that you will not have lot. It will create a lot for you. And once there is a lot number in the system you need to clear it.
But in case of skip lots, system will set the status of it accordingly, the UD of the same can be performed in mass.
And it can be set in back ground as Sujit has suggested you.
Regards,
Shyamal
Boss If you want to clear the normal lots also in auto UD then it's better to not have the lot dear.
Even though if you want to perform in mass you can use the trx QA10 for it.
Edited by: Shyamal Joshi on Dec 5, 2009 2:38 PM
Hi Raymond,
The stock always introduced in the system as per the MIGO document. So it will be posted in the storage location that is mentioned in the MIGO document.
According to your scenario you will be in need to change the stock from UR at IQA storage location to UR use to MS storage location, manually for all the skipped lots.
Regards,
Shyamal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.