Can we set a warning message in CJ20N if the users is setting a project/wbs to status TECO and there are still confirmations outstanding on the activities?

Thanks Mart

Accepted Solutions (1)

Accepted Solutions (1)

virendra_pal
Active Contributor
0 Kudos

have you checked the system

I would think this is standard

Answers (3)

Answers (3)

Former Member
0 Kudos

This message was moderated.

Former Member
0 Kudos

Hi,

TECO - Technically Complete.

Technically complete itself means that all the work that has to be done to execute the project is complete. Confirmation is done for activities and it is done when an activity is completed i.e. there is no work left to be done for the activity. If there is any work left in the activity system wont allow you to set the TECO status.

So this functionality is there in std SAP and you dont have to do anything to use this functionality.

Hope this explanation helps.

Best Regards,

Gokul

Makal
Active Contributor
0 Kudos

System will automatically throw warnings. This is standard.