Error at time of creation of process order

Former Member
0 Kudos

Dear all

I am getting following below error at time of creation of process order.

"The factory calendar does not exist (contact system administrator)

Message no. CO034

Diagnosis

An internal error has occurred.

System Response

Processing stopped.

Procedure

Contact your system administrator."

Kindly help

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Use the following path in SPRO

General seetings;;>Enterprise Structure>>Logistics General>define copy,delete,check plant.

transcation code - OX10

Check whether the factory calender is assigned to the plant or not.

Regards,

Lodhi.S

Former Member
0 Kudos

thanks all

Lodhi solved my issue

gangappab
Discoverer
0 Kudos

Hi Lodhi,

We also faced the same problem and solved with your suggestions. Thanks for this post.

Former Member
0 Kudos

please assign factory calender in OP03 t code and also check in work centre.

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Please check the factory calander maintained at plant level and as well as the resource level.Please check the factory calendar maintained at resource capacity data.

Hope this will help.

regards,

kaushik

Former Member
0 Kudos

Hi,

Please check whether the factory calender exists for that plant? Are you using startegy 11?

Regards,

satyajit