Hi,

I tried to change Base UOM for material in mass maintenance using MM17 but it gave me error when I execute it. The error msg say I need to remove stock from current and previous period but I don't understand this msg, can someone explain to me?

Accepted Solutions (1)

Accepted Solutions (1)

yann_bouillut
Active Contributor
0 Kudos

Hi Li,

Please open a thread in the "ERP" forum where MM experts will answer your question.

Kind regards,

Yann

Answers (2)

Answers (2)

Former Member
0 Kudos

See my reply in the topic

You need to clear out the stock before you change the UOM.

Do a movement 562 / 502 .. change the UOM & then bring back the stock with a 561 / 501

Former Member
0 Kudos

Hi,