Asset Under Construction

Former Member
0 Kudos

Where and how do I create an Asset Under Constrcution for a Project that already exits.

Thank you.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

creat asset with t-code: as01

and assaign it to the project, AUC will be displayed in the system status............once asset is assaigned and settlement takes place

regards

surya

Edited by: suryapampana on Dec 4, 2009 11:02 AM

Answers (2)

Answers (2)

kishore_babu15
Active Contributor
0 Kudos

Hi,

Check the below thread

For settlement to AUC settlement rule is not required. Follow the steps:

1) For WBS element where the asset has to be created, AUC willbe created automatically when the WBS element is in release status to get this investment profile should be assigned to WBS element in Control Tab

2) You can see in the syatem status show as AUC to see the AUC number follow the path

EDIT-> WBS element -


> Investment program--> Asset under Construction where you can see the AUc which is created automatically

3) Once the above two steps are throughfor settlement to AUC goto transaction CJ88 give the WBS element number select the processing type as partial captalization and execute all the costs pertaining to that WBS elements will be automatically settled to the AUC which is created for that WBS element

Regards,

Kishore K

Former Member
0 Kudos

Assign an appropriate Investment Profile on the WBS element.

Regards

Sreevas