Cost plan from alt version (other than 000) as basis for budget in CJ30

Hi Experts

I have a preimenary project structure with WBS elements (latter the network structure with reources / components will be maintained).

I have overall cost plan in CO version 'V01' and ECP in CO version 'V02'.

But none of them is proposed as Planned total in CJ30 (Maintain Budget).

Please suggest if any setting is missed.

If the planned total in CJ30 is proposed from CO version '000' only, what would be solution for preliminary planning followed by high level budgetting.

warm regards

ramSiva

Former Member
Former Member replied

In Cj30 you will get the CO version '000 , If you want to your can copy cost planning values of your version V01 & V02 to

Version 0 and do the budgeting Because you actual will happen to 0 only so, to compare your plan should be there idealy.

Apart from that network cost planning can only be done in 0 version. And system give you option of copying the your preliminary plannning to version 0.

Virendra - Thanks for the explanation. It made my understanding better as well.

With Regards

Nitin P.

Edited by: Nitin Patoliya on Dec 3, 2009 12:50 PM