What is the difference between the detailed scheduling board heuristics and the scheduling strategies. I checked both and they seem to have similar settings and options

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi GS,

Detailed scheduling heuristics in planning board talks about the

rescheduling or scheduling of operations in orders inside the

planning board interactively.

Whereas the scheduling strategy is generic which can be applied

to normal scenarios other than planning board. The various

scheduling strategies involves manual sceduling like drag &

drop methods, Schedule or deschedule individual or group of

operations, reschedule deallocated operations, optimising

scheduling etc.,

Regards

R. Senthil Mareeswaran.