Hi,
Quick Clarification:
In the SRM 7.0, Procurement for Public sector 3.0 and ECC 6.0 EHP 4 environment, when using the Extended classic scenario and Plan Driven procurement with MM-SUS integration to the supplier portal, does the PO go to SUS from ECC or SRM?
I am aware that the leading purchase order will be in SRM since it is extended classic. But with PDP and MM-SUS integration in the mix, I wanted to clarify.
Thanks,
Raj
Hi Raj,
PO will go to SUS from SRM if u are using the standard EBP-SUS integration scenario.
MM-SUS is usually used for classic scenario only.
Thanks,
Nikhil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Is this thread still valid? If not, please close the thread.
If so, as no response has been submitted, please rephrase your question and/or provide further information to describe your requirement.
Thanks
Jason
SDN SRM Moderator Team
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.