i have 3 MRP Areas in production plant and i'm doing planning using SOP.

in MC88 i can only create plan for plant level.

how can i create plans for mRP Area level

thanks

Accepted Solutions (1)

Accepted Solutions (1)

former_member667328
Active Participant
0 Kudos

Dear Essam,

Please try the following procedure.

1. Create Plan in flexible planning --> MC93 (In this step you create Sales plan in flexible planning )

2.Sales plan verification transfer to active version--> MC8V (In this step you verify and transfer to active version)

3.Transfer sales plan to production plan -->MC8Q (In this step you transfer to sales plan to production plan)

4.Create Inactive Demand in Demand Management -->MD61 (In this step you create Independent Requirement which can be

simulative requirements. These requirements are set after analyzing sales forecast and production requirements together)

I hope it may help you out..

Feel free to ask.

Thanks,

Mohit

Answers (1)

Answers (1)

madlercm
Active Contributor
0 Kudos

Hi,

True, in standard SOP you have only plant.

But in demand management (MD61/62/63) you can create and maintain PIRs at MRP area level.

If you must use SOP, then I guess that you need to look at defining your own in Flexible SOP.