on 12-01-2009 12:39 PM
Dear Friends,
I'm new into customizing in SD. I just crested a new plant, distribution channel, shipping point and have assigned the shipping point to the plant. while trying to create sales order i get this warning message "DOCUMENT /00010 HAS NO CHECKING GROUP (MATERIAL MASTER - PLANT DATA) MESSAGE N0 : W083.
Also, if i edit for incomplete log it is indicating the following as being missing- SHIPPING/RECEIVING POINT, NO LOADING DATE, NO MATERIAL AVAILABLE DATE, TRANSPORT PLANNING DATE, NO GOODS ISSUE DATE.
What else do i need to maintain in the customizing to make it work well
Thanks in advance
Hi ,
Please ensure whether you have entered :
1) Delivering Plant in material master->sales org 2 view and also plant data under sales general/plant view
2) Goto shipping tab in sales order and enter the dates mentioned in the incompletion log and proceed with the creation
Thanks & Regards,
Preethi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
It is showing because u have not maintained PLANT in MATERIAL MASTER DATA but no need to do so u can directly put into S.O. Iin each line item.
It is just a warning nmessage just press enter and pass it.
If still u want to do so then use TCODE ( MMO2) and select SALES ORG1 and under GENERAL DATA u will find PLANT FIELD
where u can maintain PLANT for matarial but once u maintain data here MATERIAL is restricted to that PLANT so will not allow u to sell it from other PLANT thats why itb is always advisable to keep it blank if you are suppose to sell same MATERIAL from two or more PLANT.
Regards
AJIT K SINGH
HAPPY TO HELP U
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.