Hi Sir,

Please correct me the following.

In my scenario I am creating a WBS & in WBS my object curreny is USD & my Co.area Currency is INR. Now from CJ30 I am uploading budget in WBS as $100.

At what basis the Exchange Rate could be calculated i.e. from USD to INR in the system.

Regards,

Gagan

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

I don't think that any calculation will be done. PS supports various currencies and I would expect that the budget will be displayed in $ and not in the company code currency.

Cheers, Aleksandra

Former Member
0 Kudos

Hi Sir,

When I am putting the budget in the WBS which inclues the object currency i.e.USD.Let us take the Eg.

Eg. Exrate as on 04/11/09-1$USD=44 inr & 01/04/09 is $1USD=41 inr. Now I am uploading the budget on 05/11/09 in the WBS.What should be the Ex rate in that WBS.

Regards,

Gagan