What is the Sequence of Master data and Transaction data R/3 to APO

Former Member
0 Kudos

Hi guys,

What is the Sequence of Master data and Transaction data R/3 to APO through CIF?

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Master data,

Material Indipendent data can be sent without any dependency.

Material Dependent data sequence is as follow.

Plant,

MRP areas,

Supply area,

Material,

MRP area material,

planning material,

ATP check,

Purchase info recards,

schedule agg,

PPM or PDS (But before PPM or PDS work center should send to apo) If PDS is sending then BOM should send before PDS.

Transaction data.

As per the business requirement what is planning in apo.

Regards,

Kishore Reddy.

Former Member
0 Kudos

thks a lot

Former Member
0 Kudos

Hi,

Master date:CIF seq

Location master

SKU loc combination

Resource

PPM /PDS

Transactional Data cif is Independent of Sequence

Preq,PO

Pl Order,PRodn Order

SO

Stocks

Thanks,Bopanna