How to set actual start without actual finish

Former Member
0 Kudos

hi all

when i want to confirm activity as partially the system asked for actual start and actual finish together. generally for actual phase in MSP it is not mandatory to fill actual finish. please advice me for this reason.

regards

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member203108
Active Contributor
0 Kudos

Amin, let us assume that you have to perform a work of 100Hrs in 10 days(01.01.09 to 10.01.09). again, assume that on 04.01.09, the work completed is 35Hrs and no actual finish date was entered for this 35hrs of work , now if your superior wants to view the progress of the project and would like to know, how many days it took to complete 35hrs of work or upto which date this 35hrs of work is completed, where will he get this information if no actual finish date was entered. You will get the information that 35hrs of work has been completed, but you will not get from when to when this work was done. That is why you have to give actual finish date also for partial confirmation.