This is Mr.Venkat here.Pls. give me the sap configuration information in step by step to the below mentioned scenario.
a]Two diff.legal entities are there.Customer will give the bulk material to the legal entity1 for packaging purpose.
b]The legal entity1 inturn will send to legal entity2 for get packed and send it to legal entity1.
c]The legal entity 1 has to send the mat to the customer.
d]The customer may/may not use sap in his business.
Pls. could you provide me the sap config. for this case.
The scenario described is similar to subcontracting Scvenario. You could certainly expect better assistance in MM forum for the same.
Regards,
Rajesh Banka
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Your requirement will be fullfilled by sub-contracting process, the steps are described in below lines:-
u2022 Create material in MM01
u2022 Create BOM in CS01
u2022 Have routing in CA01
u2022 Create sub-contracting PO with item category L - subcontracting for external procurement in ME21N, with confirmation control as inbound delivery.
u2022 Transfer goods to subcontractor with movement type 311E, using t.code ME2O. (Create an outbound delivery)
u2022 Create excise challan J1IFQ
u2022 Receive the goods from subcontractor via MIGO/ inbound delivery (Vl31n) if you have selected the confirmation control in PO.
u2022 Execute J1IFQ for reconciliation.
u2022 Update the challan via J1IF13.
Assign the sub-contracting delivery type to a shipping point under t.code OMGM.
hope this will help.
regards
Vivek.
User | Count |
---|---|
92 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.