Hi,

Suppose if we are introducing any new product and we dont have any any CVC for it in APO.

Can we do Data Realignment for this? How to introduce any new product ?

Thanks,

Prabhat

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

If you have similar type of product's CVC already available in the system, then you can realignment using copy and without 'delete source data'.

If not then you have to create new product's CVC.

Former Member
0 Kudos

Thanks Anjali,

I got the answer.

I have another question on Process Chain. I have posted that question in a separate thread.Please answer that also.

I am requesting you because you have uploaded one document on Process Chain in SAP best practices. I have downloaded that document to learn about process chain. That document is very helpful.

Thanks,

Prabhat