Hello gurus,
I have created two different structures:
- Statistical WBS Elements for allocating all the planing data.
- Internal Orders assigned to the WBS Elements for allocating all the actual data (expenses and reveues: item category of cost elements is 1).
The issue is that periodically i need to distribute these things:
- Plan data from one Statistical WBS element to others Statistical WBS elements. As the WBS Elements are statstical i really do not know how i can distribute those plan costs, i mean, how i can create the assessment cycle? which steps i must follow up? which transactions allow me to do this?
- Actual data from internal orders to others internal orders. Exactly the same questions that in the paragraph before... The problem here is that i know how to create assessment cycles using cost centres as senders, but the transaction (KSV5, KSU5) do not allow me put order as a sender
Thanks in advance for your help.
Plan data for Statistical wbs elements are not eligible for assesments/distributions and settlements.
In actuals , orders can be set as senders and receivers. Use trans KCAU to customize yur assesments.
I hope it helps.
Pan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.