detailed scheduling tab in Planed order

Former Member

Dear all

In some of the planned orders in this plant,the detailed scheduling tab is missing.

how to make the tab appear..

please help me

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member228481
Contributor
0 Kudos

HI,

Please check the corresponding formulas in Work centers, must be missing,

Formulas in Capacity tab and scheduling tab,

Run MRP with u201C2 u2013lead time schedulingu201D,

you would get the WC scheduling tab in planned orders.

Prior to that some values in Routing to be maintained.

Regards

Raghu

Former Member
0 Kudos

Hi,

I have the same issue. I have already checked the settings on the MRP run, and it is already set to u201C2u201D (Lead time Scheduling and Capacity Planningu201D). For some reasons, some of the planned orders created have missing Detailed Scheduling / Rough-cut Scheduling tabs. Could you please advise for the possible cause of this issue?

Thanks a lot in advance and have a nice day.

Regards,

lirpa

former_member311826
Active Contributor
0 Kudos

Hi

Click on the schduled planned orde tab at top ( Shift + F6). If still is does't come then check the routing lot size & your planned order qty.

Regards

Abhijit Guatam