Reporitng commitments in S_ALR_87013558

Former Member
0 Kudos

Hi Experts

I have activated commitment management for the controllling area.

But i could not see the commitment values in report S_ALR_87013558 (Budget/Actual/Commitment/Rem Plan/Assigned) for the purchase requisitions generated in the project.

Any setting is required?

warm regards

ramSiva

Accepted Solutions (1)

Accepted Solutions (1)

venkatesh_kulkarni1
Active Participant
0 Kudos

Hi

there are so many post available in the forum for other settings like value catagories - cost elements and reconstructing info system.

Venkatesh

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

if you are creating PRs through MRP then you cant see commitments but while converting PRs into POs you can see the commitments.

Otherwise if you creating PRs directly from project then you can see PR Commitement in your reports.

Also create statistical cost elements for the Inventory GL Accounts which are maintained in BSX In OBYC.

Thanks,

Muzamil

Former Member
0 Kudos

Shall explore and revert, Venkatesh