Hi,
The data entered in the field "reference" in the confirmation screen gets updated in the field "delivery note" in MIGO in R/3 system as per the standard. Now i have a requirment to capture this data from the "reference field" in SRM and pass on to the field "bill of lading" in R/3 instead of "delivery note" field. I am using classic scenario and EBP4.0 along with ECC 6.0.Can i be able achieve this requirement.
Please suggest.
Regards
GGL
don't have system now
but have you exlored this mapping via BADIS for confirmation posting
BR
Dinesh