Hi Experts,
We maintain QM operations in the Master recipe along with PP operations.
In my scenario - operations are maitained in following order
1)QM operation 1
2)PP operation 1
3)QM operation 2
4)QM operation 3
5)PP operation 2
Now untill and unless Quality validate the QM operation 1 , PP cant be able to confirm PP operation 1 .
Same like in order for operation 2 and 3.
Plz guide to map the scenarios.
Regards
saurabh
Dear Saurabh
You need to make the Sequencing also mandatory
in OPK4> For order type plant > in Generally valid settings maintain under Operation sequence > Error when operation sequence is not adhered to
By this it makes the operation 10 to be confirmed for operation 20 to be confirmed
Also make the overdelivery tolerance - error when overdelivery tolerance is exceeded
Regards
Gajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.