on 11-24-2009 11:19 AM
Folks,
we are running Heuristics in Daily Buckets. Demand in the form of Sales orders are created in ECC and are CIFed to APO. Sales order requirement time is shown as 03:00:00 ( 3 AM) in the product view ( RRP3). When i run heuristics, it creates a PR at 12:00:00 ( i.e 12 PM). Though the PR is created on the same day as of Sales Order requirement day, but because of the difference of the time, system is not pegging the PR to the S.O. Reason being Requirement time ( i.e 03AM) is before the receipt time ( 12 PM) and hence no pegging. we require pegging to be established between receipts and requirement element.
Is there any standard setting wherein we can control the time at which Sales order is shown in product view or the PR creation time ?
Pls note that we need to use Daily buckets only and pegging relationship is a must.
Regards,
Pawan.
issue got resolved
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
All,
I changed the S.O availability time in ECC to 15:00 hours so that the demand lies after receipt time and hence pegging will be there. I did this by going to schedule line and then select the shippping button. there i changed the material staging time to 15:00 hours.
I hope this helps.
regards,
Pawan.