cancel
Showing results for 
Search instead for 
Did you mean: 

investment project down payment config

Former Member
0 Kudos

Dear all

please help me on the following issue.

i am working on a investment project.

there are many POs generated with account assginment of WBS or Network.

almost every PO need to do the down payment.

but i don't know how to config it.

is it in OBYR? or somewhere else?

please give me some advice.

thanks a lot.

Judy

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear Judy ZHU,

Menctioned particular WBS cost object when ever the down payment transaction is carring out. If ur a PS consultant need not worry about this. Y because it is required some accounting knowledge regarding Reconsalation for the Down Payment. Better to hand over to FI Consultant, he will deal it. Other wise revert me back.

Regards.

Answers (1)

Answers (1)

virendra_pal
Active Contributor
0 Kudos

I do not think this is done in PS configuration

Please check with MM guys

venkatesh_kulkarni1
Active Participant
0 Kudos

Hi,

Project - costs - Actual cost and forecost-update dwn pymts where you can maintain default cost element for vendor / customer down payment.

Venkatesh