Hi Experts
The purchase requisitions generated for stock item (item cat L and AAC: Q) are not reflected as internal commitments in the report GR55 (Report group Z6P2). However i am able to see the purchase requisitions created for network (item cat N)
I believe that whether stock or nonstock, the PR should be recorded as internal commitment. Please suggest.
warm regards
ramSiva
Problem sorted out.
Missing is due to not having cost element of category 90 for the stock account relevant cost element.
regards