on 11-24-2009 10:45 AM
Hi all,
I am creating Webi Report based on SAP OLAP Universe at XI3.1, but some issues with Date Object.
Date Object Name :
Calendar Day (Dimension)
Calendar Day Key (Detail) of Calendar Day (Dimension)
i have the one day difference between above 2 objects.
means If Calendar Day Key (Detail) dispaly 24-nov-2009 but Calendar Day (Dimension) displays 23-nov-2009
Please suggest what could be the reason.
Thnx Regards,
Reddeppa K
Hi,
This issue has been fixed in BOE XI 3.1 FP1.4 and SP2.
Regards,
Didier