on 11-24-2009 9:03 AM
Hi,
We have several ways to calculate our shipment cost:
1> Per route (fixed rate) regardless of quantity
2> Per route -> fixed rate per quantity
3> Per route -> fixed rate per quantity with discount per material
4> Per leg -> shipment doc may have two legs (passing by a transfer point) point A to point B, fixed rate (#1), while point B to point C, quantity rate (either #2 or #3)
Can you let me know how to set-up in the system? 4 condition types? Should I have 4 pricing procedure for each? Should I have 4 shipment cost document? 4 Shipment types?
How to set-up in the system such that from the shipment document, I can display comparisons (if #1 or #2) option is cheaper ... At the moment, it does not prompt me comparisons.. when i click the freight cost estimate button, it gives me the value directly...
Thanks,
Hi,
There is no need to create four shipment price procedure nor to create more shipment document,
when you create shipment then under stage tab maintain stages, e.g
Stage 1 = A to B
Stage 2 = B TO C
and depending on this you can calculate cost
Regards,
kapil
Edited by: Kapildev Farakte on Nov 24, 2009 10:16 AM
Edited by: Kapildev Farakte on Nov 24, 2009 10:27 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
in shipment maintain 2 stages e.g.
Departure point A to point B
Point B to Destination Point C
Also in shipment cost type>>>Idefine team categories(0001)>>>Maintain distribution as "A"(shipment cost item)
Now create Shipment cost document by VI01, Here you will find 2 iteams( 1 is A to B and 2 is B to C),now for first you can maintain fixed price and for second you can mainatian on base of quantity.
Make appropriate calculation base in condition types.
If any problem revert back.
kapil
Edited by: Kapildev Farakte on Nov 25, 2009 6:04 AM
Edited by: Kapildev Farakte on Nov 25, 2009 6:17 AM
Hi kapil,
Thanks, but I have another question...
For example:
Option 1 = fix rate @ 5000usd
Option 2 = per quantity @ 100 per box
If for example, my delivery is less than 50 boxes, I should go for option 2.
But if my delivery is more than 50, then I should go for option 1
How then can I set this up such that the system will propose 2 instead of 1? can you give details...
(or such that I should choose to cost via 2 instead of 1) ... from my experience, it will always propose from the condition type master data... How can the system determine which one is better? Is this done manual calculation (externally)?
Thanks a lot...
Hi,
You can decide it when you creating shipment document,
whether I can create 2 stages or 1 stage, because cost is calculated on basis of
delivery
delivert item
shipment cost item
on basis of handling unit.
My suggestion is calculate on the basis of delivry Not on basis of shipment cost item (Stages).
and in shipment cost you can put manually if it is abovr 50 apply fixed cost and ig below 50 apply cost on quantity base.
Regards,
kapil
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.