WBS settlement to CO-PA

Former Member
0 Kudos

Dear Experts,

We have PS in place and current process for prototype is that we assign WBS to PP order and PP order is real cost object and PP order is settled.

We have sales order also with WBS element (same as PP order) and we want to settle this WBS element so as to reflect in CO-PA .

But you cannot maintain RA key in PP order as well as WBS.

what would be the possible solution.

Regards,

Apps

Accepted Solutions (0)

Answers (1)

Answers (1)

virendra_pal
Active Contributor
0 Kudos

settle cost to WBS

use WBS as the object for running RA and settling to CO-PA