Hi, All
Picking Date
Trans. Planning Date
Loading Date
Planned GI Date
Delivery Date
As listed above, there are scheduling dates in Delivery, if I change one date manually, how could I make the other dates update automatically?
By backward/forward scheduling in the system, the schedule is determined automatically for ATP and the date would be copied from scheduling line of SalesOrder to Delivery docuemnt.
The duration between each two dates are calculated base on the settings of ShippingPoint and Route.
So...any solution out there?
Regards,
Michael
Hi,
The "Pick/Pack time" & "Loading time" comes from the Shipping point.
The "Transit time " and "Transportation planning time" comes from the Route.
Considering the above times, system calculates the "Material availability date", "Transportation planning date", "Loading date" , "Goods issue date" and "Confirm delivery date" automatically.
To understand how the system calculates the above times automatically please refer this below link:
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi;
This is not possible simply because there is no Schedule line level in the delivery document. As far as I know the only thing that can be updated in the delivery is the actual GI date and the Pick date.
Regards,
Mani
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.