Hi there,

I'm going to start a new TDMS TDTIM project in a 2 system ERP landscape with only production and development system. My setup would be to use production also as central/control system and I would use a new client built as a SAP_UCUS copy of client 000 for TDMS.

I assume that it would cause problems during the deletion phase if i would use the receiver as c/c system.

Are there any known problems with sender and central/control on one system?

Many thanks in advance.

Marc Wagner

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Marc,

The sender system can also serve as the central system if it is on basis release 620 or higher. Any of the systems except the receiver system may be chosen as control system. The reason why the receiver system should not be used as the central system or control system is that the historical data for SAP TDMS needs to be stored permanently, while the receiver system

is meant to be refreshed at regular intervals.

Please refer to the security guide for more details.

Srila.

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Marc

You may have your central/control system on either sender or receiver, you should not face any issues.

Best regards