on 11-23-2009 12:26 PM
Hi Friends
I have one requirement ,
i.e
1. Material issue to the production against production order for 10 qty(5 rejected in production)
2. sent to QC for reinspection for 5 qty
3. How to move this qty to qc
4. QC will take 1 week to complete re inspection
5. How production guy replace this 5 qty immediatley from store
Please let me know the settings,
Thanks & Regards
Gajendranath
Hi
1. Material issue to the production against production order for 10 qty(5 rejected in production)
2. sent to QC for re inspection for 5 qty
3. How to move this qty to qc
When you issue the material it is 261 against the Production order.
So when 5 material is rejected in the production ,you will actually make the Confirmation of 5 Qty in CO11.Rest of the Quantity you can do 262.
Now Move this material to "QUARANTINE STORAGE location" like QRNT( only for rework ) .storage location where you will physically & in system ..carry out the rework.This can be done by Mvt type-311 in MB1B.
4. QC will take 1 week to complete re inspection
If Material After rework is ok then only again move material back.
5. How production guy replace this 5 qty immediatley from store
He can reissue material by 261 against reservation MB21 & then by MB1A against the reservation.
I hope this will help
Regards
Sujit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Gajendra
Please find the steps
Rework & rejection
1. Reverse faulty material using Tcode MB1A u2013 262 movement type against the production order
2. Move the material to block stock
3. issue ok stock from existing stock by 261 movemnt to production order
4. Create a rework order using Tcode Co01 order type (PP03)
5. Enter the Parent production order number in the goods receipt tab in Co01. (inbound delivery)
6. Issue goods against the rework order using MIGO
7. confirm the rework order through co11n
8. Move the material back from block to quality using Tcode MB1B u2013 349 movement type (activate 08 inspection)
9. Inspection lot created
10. do the posting accordingly
Regards
Gajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.