Dear All,
we are creating process order here automatically Recipe group will select.
And the Inspection lot becomes "REL" Status, so if we go to QA02 it will not allow to change the Recipe group.
Please suggest where we can change the Inspection plan for the particular material from old to New.
Regards
DON
Thank you all
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Don
If you the inspection lot is CRTD or REL stage then there is another method to attach a new routing group
1) Go to CO02 and enter
2) Menu Button Function > Read PP Master Data
3) A pop up will come for Yes / No, Say Yes,
4) Another pop will arrive, click on continue
5) Another pop up will appear > Make sure that the tick on New Routing and New BOM is available. Enter
6) Select the new group of routing and enter
7) order status will change to CRTD , Release and save it
The inspecion lot will automaticaly gets attached with new group
Hope this helps
Regards
Gajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Don
As you said "Under Insp Specification Tab "Task List/Spec" and under Sample tab "Smpl" is active but other fields are grey mode"
If these fields are active then click on the Task List/ Spec button and then on the sample tab on Sample
this will assign the new group
Meanwhile i will also run one cycle and let you know
Regards
Gajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please again do the following things
this has to work
1) Go to QA02
2) Menu > INspection lot > Reset Sample
3) Enter & Save
check status of lot CRTD
4) QA02
5) Inspection specification > Assign task list by click on Task/ specification
6) Go to Sample, do the SAmple calculation
7) Save
😎 Check whehter lot status is REL
Regards
Sujit
Dear Don
You can go to Qa02 > inspection specification > click on Task/ speclist & in Sample tab click on Sample and then save and refresh
Regards
Gajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Don
if any confirmation for the order or any result recording done it wont allow you to reset the sample.
Only way to assign new inspection plan is to cancel the order and create a new one
Regards
Gajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Don,
You can try using transaction QAC3 to reset the sample of the inspection lot, this will set the status of the lot back to CRTD. You can then manually do the task list assignment to the new task list required.
Regards,
Roderick
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.