on 11-20-2009 5:22 PM
Hi All,
Background job X will run on daily basis and which in turn triggers two jobs say A and B.
The job X got finished successfully but jobs A and B havn't been triggered and so not running.
Please help me on this.
Thanks & Regards,
Gopi L.
most of the time , removing the jobs and redefining them should solve the problem.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
Gopi check the start condition of job A & B, what event is triggering these jobs.
Also check SAP note 395170.
Regards,
Sachin Rane.