We have an issue where we want to change the Requestor and goods recipient for PO's in SRM as the requestor is leaving the organization. Do we have any way possible to change the Requestor adn goods recipient for SRM PO's?

I have found bbp_crr, but it only list partly confirmed/invoiced POs. I'm not sure if the transaction is suppose to do the mass change.

Thank you

Joann

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hello,

The report BBP_CRR suggests all the POs assigned to a requisitioner , that are to be assigned to a new requisitioner/recipient and that are not closed.

Once the POs are suggested , you can change for all the POs or make your own selection.

Hope this information was useful.

Regards,

Kalyan

Former Member
0 Kudos

A custom program was written to do mass PO change to requisitioner and goods recipient.

Regards,

Joann

Former Member
0 Kudos

Hi Joann,

Did you get to resolve this, if yes, please share the solution.

Using BBP_CRR transcation, i am not able to modify the requestor in SRM PO.

Please suggest.