If supplier is unable to submit all items at once, do we have PO splitting at SUS side along with diff delivery dates if supplier is unable to submit total qty at once.
How to monitor the all the changes made to a document by buyer. Do we have version control in std
Are there any Std reports bet MM-SUS and viceversa
Regards
Andrew
thanks friends
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Andrew,
The vendor can accept the PO quantity partally or can also change the delivery date. However this will trigger the PO Change process and buyer has to send back the changed PO again if th buyer is ok with it. It is not possible to directly split a line into multiples lines. the only option available for the vendor is to change the price,quantity and delivery date.
Yes, there is historial versions available on SUS PO.
I dont thnk that there any standard reports bwteen MM and SUS.
Hope this answers your questions.
Best Regards,
Pavan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.